top of page
IMG_9867.jpg

Projects - Updates on ongoing projects
Last Updated on July 17, 2026

Lake Pointe Boat Dock Project

Contractors began construction of a two-slip day dock for Lake Pointe residents’ use on June 1st in hopes to return lake access to residents as quickly as possible. Construction on a new separate two-level swim dock began on July 13th with an expected completion date of October 1st, in line with the original expectation of 120 days of construction. The LPMUD is committed to opening both docks for use when they are completed and can be opened safely. At this time the project committee is exploring options to open the two docks at different times, with the day dock being accessible sooner than the swim dock.  

The waterfront at Lake Pointe remains closed to accommodate this construction. While not ideal, the existing floating dock was removed so crews could safely install new pilings and structures in its place; the board chose this option following significant deliberations to avoid safety risks to residents and regulatory issues.

 

Click image below to see a rendering of the dock design.

01 JUN AI Dock Rendering v2-281px.png

Vista Pointe Park Improvement Project

The district awarded the bid to a contractor for the major upgrade at Vista Pointe Park, including a new restroom facility and other park improvements.
The restroom design is a compact masonry building (about 10x10 feet) intended to fit the look of the park and neighborhood; detailed plans have been shared with the LPHOA for review in hopes that the same design can be reused in Napa Park, resulting in cost savings on design. 

Separately, the board has approved a contractor’s bid to build and relocate the Lake Pointe Preserve vehicle gate that is at Vista Pointe Park. The location of the new vehicle gate will be at the back of the park, just as the lake access road begins and will allow less restrictive access to Vista Pointe Park for residents of the district. In addition, new pedestrian access to the lake road and LP Preserve is being designed. The current vehicle and pedestrian gates will remain in place until a later time when they can be decommissioned effectively.

Lake Pointe Wall Project

The district attorney has formally requested conveyance of the existing fences and footer wall and remaining monuments from the LPHOA and the attorneys are working through the details of conveyance. The LPMUD board must delay major design spending until those discussions are complete and conveyance is imminent. The LPMUD has offered to form a joint committee with the LPHOA for the LPHOA to provide high level feedback on design elements of the wall and monuments. Updated survey work for the neighborhood wall replacement is complete, and the engineer is ready to move into full design and permitting once property and conveyance is underway.

Lake Pointe Pedestrian Trailhead Parking Area

The new trailhead parking area in the LP Preserve is complete and open, with clear signage and designated areas for vehicles and golf carts. The LPMUD is delighted that the parking area is being used properly by families accessing the trails, and parking appears orderly. The LPMUD is actively monitoring drainage and roadbase erosion and may implement further design elements to slow such erosion.
To protect nearby roads and trails from storm damage, the district approved a drainage project that will add a drain and inlets to better capture and redirect stormwater away from the PUA facilities and preserve trails. The start of this construction is imminent and expected to complete in plenty of time for the reopening of the waterfront to residents.

Lake Pointe Entrances & Monuments Replacement

The district’s engineer and landscape architect have prepared concept designs for new entry monuments that comply with City of Bee Cave and Travis County sign ordinances for each of the Lake Pointe entrances.
Before moving into full design and permitting, the board has shared concepts with the LPHOA and is awaiting feedback. The necessary next step will be for the LPHOA to convey the remaining monuments at Bayton and Napa Drives and any Travis County or TXDOT rights of way agreements to the LPMUD.

Bond Application and Issuance

The Board has amended its preliminary engineering report to include the trailhead parking area and Vista Pointe Park projects, ensuring the final bond application accurately reflects all planned improvements.

The LPMUD board is currently engaged with Bond counsel to understand the best time to issue bonds and begin the process. There is no immediate rush to issue bonds, as the District can currently fund the initial steps of the projects using existing reserves and seek reimbursement at a later date. 

Create a beautiful creek in the woods with trees.png

Bond Projects
Lake Pointe Boundary Fence Survey – Access to Resident Property - View Announcement | View Map
Signed Order Canvassing Election Returns - View Here
Notice of Election - View Here
Official Ballot Language - View Here
Order Calling Bond Election - View Here
Sample Ballot - View Here

Lake Pointe Municipal Utility District (LPMUD)
Frequently Asked Questions (FAQ)

What’s happening in Lake Pointe?

The Lake Pointe Municipal Utility District successfully passed a bond election on May 3, 2025. The Board is now funding key capital projects throughout the neighborhood.
____________________________________________________________________

How much will these projects cost?

The approved funding for capital improvements is up to $8 million.
____________________________________________________________________

How are the projects being funded?

Funding comes from municipal bonds, with repayment spread over 20–25 years through resident property taxes. The current estimate aims to keep the impact below $0.05 per $100 of appraised value. Costs are not expected to exceed $0.07 per $100.
____________________________________________________________________

Which projects are currently underway?

Wooden Boundary Fence Replacement

  • Replacing wooden fences with stone walls along Resaca Blvd, Sonoma Drive, and the eastern edge of the neighborhood.

Swim Dock Replacement

  • The old floating dock is being replaced with a larger, stationary, double-deck dock.

  • Designed for safety and simultaneous use by multiple families.

New Day Slips

  • A separate structure near the dock with two day slips for loading/unloading vessels.

Entrance Signage

  • Upgrading all entrances off Bee Cave Rd with modern monuments, lighting, and features.

Vista Pointe Park

  • Adding restrooms, a new playscape base, pavilion upgrades, and permanent playscape benches.

Napa Park

  • Planned enhancements include restrooms, pending final arrangements with LPHOA.

____________________________________________________________________
What is the project timeline?

Projects are phased over the next few years. Some projects are already underway, including the swim dock replacement.
____________________________________________________________________

Who maintains the new amenities?

Maintenance for all new facilities, including restrooms and docks, is included in LPMUD’s annual operating budget.
____________________________________________________________________

Who oversees these projects?

LPMUD works with experts including the District Engineer (KFM) to manage projects like the stone walls and new dock.
____________________________________________________________________

Will LPMUD indemnify the LPHOA?

The LPMUD will retain ownership of the new amenities, maintaining sovereign immunity. In the case of Napa Park, a legal easement will be arranged.
____________________________________________________________________

How will restroom access be managed?

It’s likely that restrooms will be accessible during the day and secured at night. Final specifications are still being finalized.
____________________________________________________________________

Will restrooms be added near the dock?

No. Changing coves are included on the dock, while new restrooms are at Vista Pointe and Napa Parks.
____________________________________________________________________

What will be the height of the new stone walls?

Walls are estimated at 8 feet, but actual heights will mostly match the existing fences.
____________________________________________________________________

Does Lake Pointe carry insurance for the new facilities?

Yes. Insurance is factored into LPMUD’s annual budget.

bottom of page